Client: FSUE Rosmorport

Project schedule: 2017-2020

Project brief


A number of defects have been detected in berths 1 and 2 of the port of Petropavlovsk-Kamchatsky, and berth 3 has been taken out of service.

In addition, since the berths were constructed, the regulatory requirements for the seismic resistance of structures have been revised, leading to the need for their reconstruction.

Work completed to date

Morstroytechnology has completed the following tasks for this facility:

  • engineering survey work
  • project design and cost-estimating documentation
  • all necessary expertise approvals have been received

Main project characteristics

The Cape Signalny complex included the following facilities:

  1. Federal-owned facilities
  • Cargo berth for receiving and handling design vessels (reconstruction of berths 1 and 2)
  • Cargo berth 3
  • Operational basin for ​​berths with necessary navigation equipment
  1. Investor-owned facilities
  • Rear storage areas
  • On-site engineering and technical support networks
  • Crane runways
  • Checkpoint buildings 1 and 2 and fencing of the territory to ensure transport security.

Construction stages:

  • Stage 1 - reconstruction of hydraulic mooring structures, taking into account prospective design vessels. In connection with the priority of financing in the composition of stage 1, the allocation of stage 1.1 has been envisaged
  • Stage 2 - creation of the compex’s coastal infrastructure

According to the technical brief, the reconstruction of hydrotechnical structures entails alterations to their purpose, design vessels and operational capacity.

Berth design function:

  • berths 1 and 2: handling of general and container cargo
  • berth 3: mooring for port vessels
  • the shoreline reinforcement of berth 1 is repurposed as a cargo berth.

Estimated cargo turnover – 680,000 tonnes.

The floor loading from the cargo planned to be handled at the berths is up to 10t/m2, which exceeds their standard operating loads in their current state.

Preliminary consideration was given to a range of options for the design of the hydrotechnical structures: a sheet pile edging secured with bolts, and a high pile foundation grid with a front sheet-pile edging wall. A high pile foundation grid with a reinforced concrete topside and a front sheet-pile edging wall was adopted as the main reconstruction option.

Structural cross-section

3D cross-section

Transport fleet vessel loading and unloading is planned according to the following technical paths:

  • Ship - crane - truck / vice versa
  • Ship - crane - temporary storage area / vice versa
  • Ship - crane - port tractor-unit/trailer (intraport transport) - storage area
  • Ship - crane - forklift (intraport transport) - storage area
  • Ship - quayside portal crane (or manipulator) - rear portal crane - storage area
  • Warehouse - crane - truck / vice versa
  • Warehouse - loader - truck / vice versa
  • Warehouse (temporary warehouse) - crane (loader, tractor-unit/trailer) - warehouse / vice versa”.

Container-handling at the complex’s projected berths

Key features of the project

The hydrotechnical structures are being designed with the seismicity of the construction site taken into account. In the event of an earthquake, the berths should not sustain any damage.

Data on regional seismicity is incorporated into regulatory documents. These norms have been updated in 1962, 1969, 1981 and 2014. Each edition is accompanied by updated maps of general seismic zoning, which are used to determine the seismicity of the area. According to the maps, seismicity has increased in some areas by 1-2 points. This has affected the ports of Novorossiysk, Tuapse, Sochi, Petropavlovsk-Kamchatsky, Makhachkala and others.

But the berthing facilities in these ports have already been constructed. For the sake of safe operation going forward, all these structures require additional seismic reinforcement.

In the case of the port of Petropavlovsk-Kamchatsky, it was necessary to find the most cost-effective method of reconstruction for an operating enterprise